top of page

Project Schedule

Provided below is the current schedule for conducting the environmental impact study process outlined by the National Environmental Policy Act, including opportunities for stakeholders and the public to share comments and provide input. The schedule, subject to change, has been updated periodically over the course of preparing the Draft and Final Environmental Impact Statements and leading to the Record of Decision.

Milestone

Notice of Intent to Prepare Draft EIS

Public Scoping Process

Public Scoping Meeting (Letcher County)

Publication of Draft EIS

Public Review of Draft EIS

Draft EIS Public Meeting (Letcher County)

Draft EIS Public Comment Period Ends

Publication of Final EIS

Public Review of Final EIS

Record of Decision

​

Schedule

September 28, 2022

September 28, 2022 - November 30, 2022

November 17, 2022

March 1, 2024

No less than 45 days following Draft EIS publication

March 28, 2024

April 15, 2024

July 12, 2024

No less than 30 days following Final EIS publication

Late October 2024

bottom of page